With
the demand of the market,
UPS is widely used in various industries, and the
battery has become the power guarantee for the
uninterruptible power supply system. When
the mains are abnormal, the battery converts chemical energy into electrical
energy, which is converted into AC electrical energy through the inverter in
the UPS and delivered to the load to ensure uninterrupted and continuous
operation of the load.
Valve-regulated maintenance-free sealed
lead-acid batteries
https://www.everexceed.com/lead-acid-battery_c1 have been widely used in large, medium and
small UPS,
accounting for 1/4 to 1/2 of the total cost of UPS. According to the survey,
the life of the normal use of the battery is generally about 5 years, and about
50% of the UPS failures at the end of the use are related to the battery. The
failure of the battery is mainly manifested in the backwardness of individual
batteries or the low floating charge voltage of the battery, the short backup
time (insufficient capacity), and the UPS that needs to be started by the
battery cannot be started with load when the mains is abnormal. In order to
ensure the normal operation of the UPS system, it is necessary to formulate a
reasonable maintenance plan especially for the condition of the battery.
1 Battery float voltage monitoring
(1) Medium and large UPS is generally equipped
with a monitor. By monitoring and setting the upper and lower limits of the
float voltage, the health status of the battery can be monitored at any time,
and abnormalities can be dealt with in a timely manner.
(2) Use a multimeter to measure the float
voltage of the battery.
Through the above method, referring to the
standard of YD/T799-2002 "Valve-regulated sealed lead-acid battery for
communication", the floating voltage deviation of the battery in the
floating state is not more than 480mV (12V battery). If the test voltage
deviation is large, it is necessary to consider changing the Observation and
testing are carried out after switching to the homogeneous charging mode. If
there is no improvement after switching to the floating charging mode, the
following methods should be considered for testing and verification.
2 Capacity test
of battery In general, the following capacity
test methods can be selected when conducting regular capacity test of battery.
2.1 Off-line measurement method (if conditions
permit)
(1) After the battery pack is fully charged,
leave the UPS for 1 hour, and connect an external (intelligent) dummy load at
an ambient temperature of 25°C±5°C. 10-hour discharge rate for discharge test.
(2) The terminal voltage, ambient temperature
and time of the battery should be measured before the discharge starts.
(3) During the discharge period, the terminal
voltage, discharge current and indoor temperature of the battery should be
measured and recorded. The measurement time interval is 1h, and the discharge
current fluctuation should not exceed 1% of the specified value.
(4) During the discharge period, the terminal
voltage and room temperature of the battery should be measured and recorded,
and the measurement time interval is 1h. To be measured at any time at the end
of the discharge period, in order to accurately determine the time to reach the
discharge termination voltage.
(5) The discharge current multiplied by the
discharge time is the capacity of the battery pack. When the battery is
discharged at a rate of 10 hours, if the temperature is not 25°C, the actual
measured capacity should be converted into the capacity Ce at 25°C according to the following formula:
Ce=Cr/[1+K(t-25°C)] ( 1)
In the formula: t—ambient
temperature during discharge
K—temperature coefficient
(10-hour rate discharge, K=0.006/℃;
3-hour rate discharge, K=0.008/℃; 1-hour rate
discharge, K=0.01 /℃)
(6) After the discharge, the battery pack should
be charged, and the charged power should be more than 1.2 times of the
discharged power.
2.2 On-line measurement method
(1) In the
DC power supply system,
adjust the output voltage of the UPS to the protection voltage, supply power to
the actual load from the battery, and find the battery with the lowest voltage
and the worst capacity in the battery pack during discharge as a capacity test
object.
(2) Turn on the UPS to charge the battery pack,
and wait for the battery pack to be fully charged for more than 1 hour.
(3) Carry out a 10-hour rate discharge test on
the battery with the worst discharge in (1). Measure and record the terminal
voltage, temperature, discharge time and room temperature of the battery before
and after discharge. In the future, measure and record every 1h. When the
discharge is approaching the termination voltage, it should be measured and
recorded at any time in order to accurately record the discharge time.
(4) The discharge current multiplied by the
discharge time is the capacity of the battery pack. If the room temperature is
not 25°C, it should be converted into the capacity at 25°C according to formula (1).
(5) After the discharge test, use the charger to
supplement the battery to restore its capacity.
(6) Draw the discharge curve according to the
measurement record data.
2.3 Checking discharge test method
In order to know the approximate capacity of the
battery pack at any time, it is necessary to carry out a checking discharge
test load power supply. Before and after the battery pack is discharged, the
terminal voltage, temperature, room temperature and discharge time of each
battery should be measured and recorded. Release 30% to 40% of the rated
capacity.
(2) After the discharge, the battery should be
charged, and the charged power should be more than 1.2 times the discharged
power.
(3) Draw the discharge curve according to the
data recorded by the measurement, and reserves it for comparison when measuring
again in the future.
Note:
(1) For the battery pack of the UPS power supply
system, it is not recommended to use the offline measurement method for
capacity testing.
(2) When conducting the online measurement
method and the check capacity test, for the UPS equipment with the battery
discharge test function, it is necessary to turn on the battery discharge
detection function to conduct the battery discharge test. For a UPS without
this function, it is necessary to turn off its AC input power supply and
conduct a discharge test.
2.4 Precautions
(1) It is very important to ensure the operation
of the system during the capacity test. Therefore, during the capacity test, it
is necessary to know in advance whether there is a planned power outage in the
mains, and the standby generator set should be in good condition.
(2) Before carrying out the battery capacity
discharge test, use a multimeter, an internal resistance meter, and a
conductivity meter to conduct a preventive test on the performance of the
battery.
(3) In order to ensure the accuracy of the
capacity test, professional battery capacity online test instruments and dummy
loads should be used for the test.
3 Test of high current output at the moment of
battery startup
In the actual use process, the switching time of
the
backup
UPS from
the mains power supply to the inverter power supply is required to be less than
7ms, and it is generally designed to be 4 to 5ms. When the mains power supply
is abnormal, the battery must output what the load needs in less than 4-5ms.
If you have any requirements or any kind of
query regarding the UPS solutions, feel free to communicate with our dedicated
team at any time at marketing@everexceed.com.